Question 1

A development team is attempting to use Scrum as its process framework. You join the
team as the new scrum master.
During a meeting, a developer states that his "task is done."
You need to describe to the team how the word "done" relates to Scrum.
What should you do?

Question 2

Your development team uses Scrum as its process framework and utilizes the Microsoft Framework (MSF) for Agile Software Development 6.0 process template.
A new team member who is new to Scrum assumes the role of product owner.
You need to help the new product owner prioritize the product backlog.
Which basis should you suggest the new product owner use for prioritizing the product backlog?

Question 3

Your network environment includes a multi-tier Microsoft Visual Studio Team Foundation
Server (TFS) 2012 server implementation.
A member of the networking team changes the name of a user's computer.
From the user's computer, you need to modify the existing workspace to reflect the new computer name.
What should you do?

Question 4

You are using Microsoft Test Manager (MTM) to manually test for an ASP.NET website. You have previously created a test plan named QA Release 1.0 that contains 115 test cases, and you are now planning the testing for Release 2.0.
The QA Release 2.0 test plan must meet the following requirements:
- All the test cases in QA Release 1.0 should be available in QA Release 2.0.
- Testers should be able to change, add, or remove test cases from either the QA Release 1.0 test plan or the QA Release 2.0 test plan as required, without affecting the other test plan.
- Shared steps and test configuration from the QA Release 1.0 test plan need to be reflected in QA Release 2.0 test plan.
You need to facilitate simultaneous testing of the website by creating the QA Release 2.0 test plan according to the stated requirements.
What should you do?

Question 5

You are using Microsoft Test Manager (MTM).
You need to develop test cases that trace to a set of requirements.
What should you do?