Question 1

You are a project manager who uses Project Professional 2013.
Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week.
You need to set up their calendars to reflect the job-sharing arrangement.
What should you do?

Question 2

You use Project Professional 2013 to manage a project schedule which includes all task relationships.
The resource who is assigned to the "Develop software delivery" task is no longer available to work on your project. You can find another resource to perform this task, but you are not sure when the resource will become available.
You need to know which future tasks could be affected as a result of the resource leaving your project.
What should you do?

Question 3

You use Project Professional 2013 to manage a project for your organization.
You are tracking work in a project which contains a baseline and resource assignments.
You want to view the work variance for a specific resource for a specific task.
You need to choose a view that will show this information.
What should you do?

Question 4

You are a project manager who uses Microsoft project.
Your manager wants you to plan an office move. You have a project schedule from a prior office move named OfficeMove.mpp.
You need to create a new project schedule based on the old project schedule by performing the fewest steps possible.
What should you do?

Question 5

Your company uses Microsoft Project, and you are setting up an initial planning schedule.
You need to make sure that all new task durations are shown as estimated.
What should you do?