DRAG DROP
You are a project manager for an organization that uses Project Server 2013.
You check out a project for editing in Project Professional 2013 and discover that one resource is overallocated across three projects.
You need to determine the cause of the overallocation by using the Team Planner view to resolve the issue.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)
You work for an organization that uses Project Server 2013. Single-entry mode is disabled.
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
During week one, a team member enters a total of 20 hours of actual work.
During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value
decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?
You are a project manager for an organization that uses Project Server 2013. Synchronization is enabled. Project Sites at your organization are created by a default template when a new schedule is published.
You are the Project Owner of a schedule. You have a Project Site associated with this schedule.
You need to quickly change the look and colors of your schedule's Project Site.
What should you do?
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Enterprise Gantt Chart is visible to all project managers.
You plan to create a new project enterprise custom field to show information about schedule variance.
You need to include this new field in the Enterprise Gantt Chart in Project Professional 2013 so that all project managers of actual and future projects who use this view can see this field by default.
What should you do?