HOTSPOT
You are the project manager for a real estate management company. You are using
Microsoft Project to manage the development of a new restaurant. The schedule includes a task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2016.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.
HOTSPOT
You use Microsoft PPM to manage projects. You plan to use milestones in a project.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
HOTSPOT
You use Microsoft PPM to manage projects. You plan to add risks and issues to a project.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent.
You need to create a new prioritization that includes the additional business driver.
What should you do?
DRAG DROP
You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.