You are a project manager for a company that uses Project Professional 2013.
You are developing a schedule and plan to use the leveling order of Priority, Standard.
You need to create a task which leveling will not change.
What should you do?
You manage a project by using Project Standard 2013.
You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2.
What should you do?
You are a project manager for a large telecommunications company that uses Project Professional 2013.
The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task.
You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project.
What should you do?
Your organization uses Project Professional 2013 and records actual hours worked on the project.
You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.
The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.
You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)
You are a project manager who uses Project Standard 2013.
Your current project has resources with the standard calendar as the base calendar. Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks. When you assign a resource to one of these tasks, you get an error.
You need to correctly assign the resource.
What should you do?