You are a project manager who uses Project Professional 2013.
A customer has sent you a project plan, which contains several custom fields that you want to use in your project. You have a custom field named CF1 in the Number1 field in your project, and you have a custom field named CF2 in the Number1 field of your customer's project.
You need to copy the custom fields from your customer's project into your own. You do not want to overwrite your project custom field.
You open both projects.
What should you do next?
DRAG DROP
You are an independent project manager who uses Project Professional 2013 and wants to extend the standard functionalities of it.
You need to find and install an app from the Office Store.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)
Your company uses Project Professional 2013. You are a program manager who has a master project created for your program.
Currently you are seeing the critical path for each independent project in the master project. As a program manager, you want to ensure the resources are properly applied to successfully complete the program.
You need to display the critical path for the entire program instead of each independent project.
What should you do?
You are a project manager for an organization that uses Project Professional 2013.
You are planning a project schedule that starts on March 1 and lasts four months.
However, the sponsor now asks that the project be delayed to have a finish date of December 31.
You manage a project schedule by using Project Professional 2013.
You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00.
You need to view graphically which tasks and resources are causing the $5,000.00 cost variance.
What should you do?