MB-320 Exam Question 51
You are the production scheduler for a manufacturing company. You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.


After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.

MB-320 Exam Question 52
You need to set up the configuration model to price the motorcycles correctly.
What should you do?
What should you do?
MB-320 Exam Question 53
A manufacturing company uses license plates for inventory tracking of all materials. Part M92020 is stored with 30 units for each license plate. You create a production order that indicates one unit of part M9202 and release the order for picking. There is no inventory currently available in the production input location.
The warehouse fast-tab setup for part M92020 is shown below.

Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic. NOTE: Each correct selection is worth one point.

The warehouse fast-tab setup for part M92020 is shown below.

Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic. NOTE: Each correct selection is worth one point.

MB-320 Exam Question 54
A company makes engine parts used in the automotive industry.
They are in the process of retooling an existing manufacturing plant. They are looking to use Dynamics 365 for Finance and Operations to help support the Bill of Materials (BOM) product lifecycle for engineering version control.
You must translate existing production processes into the proper elements. You need to create BOM lifecycle states to translate existing production processes into the proper elements.
What type of BOM product lifecycle state should you create? To answer, select the appropriate BOM state in the answer area.

They are in the process of retooling an existing manufacturing plant. They are looking to use Dynamics 365 for Finance and Operations to help support the Bill of Materials (BOM) product lifecycle for engineering version control.
You must translate existing production processes into the proper elements. You need to create BOM lifecycle states to translate existing production processes into the proper elements.
What type of BOM product lifecycle state should you create? To answer, select the appropriate BOM state in the answer area.

MB-320 Exam Question 55
You have updated a cost category price from $5.00 to S7.00. You process a production order which uses the cost category. After ending the order, you realize a new standard cost was not calculated after the price update.
You need to validate how this impacted the financial voucher transactions. What transaction would you see in the general ledger?
You need to validate how this impacted the financial voucher transactions. What transaction would you see in the general ledger?