MB-320 Exam Question 61
A customer produces light projection toys for holiday decorations throughout the year. Vendors have negotiated rebate agreements as a condition of their contract. The contract also contains the visual templates required for the customer to use in a season.
Vendor rebate agreements must only be applied if the following requirements are met:
* Units of measure for deliverables are the same unit of measure as on the agreement.
* The agreement is valid as of the date a purchase order is generated.
You need to configure the vendor rebate agreements. What should you do?
Vendor rebate agreements must only be applied if the following requirements are met:
* Units of measure for deliverables are the same unit of measure as on the agreement.
* The agreement is valid as of the date a purchase order is generated.
You need to configure the vendor rebate agreements. What should you do?
MB-320 Exam Question 62
A company manufactures automobile engines.
You must create product configurations for values that are used in different types of engines. Each value is based on a master valve design. Different gaskets and fittings are used to allow valves to work with different engines.
You need to translate production plans into Dynamics 365 Finance and Operations elements.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You must create product configurations for values that are used in different types of engines. Each value is based on a master valve design. Different gaskets and fittings are used to allow valves to work with different engines.
You need to translate production plans into Dynamics 365 Finance and Operations elements.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Exam Question 63
A company uses manufacturing execution for processing of production orders.
Multiple production orders from last week need to be ended.
You need to process the time registrations to allow the orders to end.
Which four steps should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Multiple production orders from last week need to be ended.
You need to process the time registrations to allow the orders to end.
Which four steps should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Exam Question 64
You are the production scheduler for a manufacturing company. You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.


After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.

MB-320 Exam Question 65
A company plans to implement Dynamics 365 for Finance chain Operations.
You need to determine which manufacturing solutions to use.
Which manufacturing solution should you use? To answer, drag the appropriate setting to the correct drop targets. Each source may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

You need to determine which manufacturing solutions to use.
Which manufacturing solution should you use? To answer, drag the appropriate setting to the correct drop targets. Each source may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.