MB-330 Exam Question 71
You need to configure the products for the requirements.
Which configuration should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Which configuration should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

MB-330 Exam Question 72
A company uses Dynamics 365 Supply Chain Management.
You need to implement inventory cycle counting.
Which counting methods should you use? To answer, drag the appropriate counting methods to the correct requirements. Each counting method may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

You need to implement inventory cycle counting.
Which counting methods should you use? To answer, drag the appropriate counting methods to the correct requirements. Each counting method may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

MB-330 Exam Question 73
You are the planner for a distribution company.
You observe an increase in planned orders for item C0001. You must track the source for these planned orders and break them out based on their demand. You are not concerned with safety stock maximums for this item.
You need to ensure that the master planning batch job will create a unique planned purchase order for every new demand requirement for C0001.
Which coverage code should you use?
You observe an increase in planned orders for item C0001. You must track the source for these planned orders and break them out based on their demand. You are not concerned with safety stock maximums for this item.
You need to ensure that the master planning batch job will create a unique planned purchase order for every new demand requirement for C0001.
Which coverage code should you use?
MB-330 Exam Question 74
A company uses Planning Optimization.
A customer calls a service agent at the company and asks about product availability dates when placing an order.
Capable to promise (CTP) is initiated from the customer's order.
What is the expected output?
Select only one answer.
A customer calls a service agent at the company and asks about product availability dates when placing an order.
Capable to promise (CTP) is initiated from the customer's order.
What is the expected output?
Select only one answer.
MB-330 Exam Question 75
A company uses the built-in master planning engine but plans to use Planning Optimization instead. You enable auto-firming. You need to ensure that planned orders are firmed within the current month. What should you do?