MB-335 Exam Question 71
A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin.
You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents pad of the solution.
NOTE: Each correct selection is worth one point.
You must account for paint drying time before assembly operations can begin.
You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents pad of the solution.
NOTE: Each correct selection is worth one point.
MB-335 Exam Question 72
A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
MB-335 Exam Question 73
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE:Each correct selection is worth one point.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE:Each correct selection is worth one point.

MB-335 Exam Question 74
A company plans to account for indirect costs related to materials used to manufacture products.
The items used to manufacture products have surcharge rates that depend on the type of product being used.
You need to set up the costing sheet to include surcharges for specific items.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

The items used to manufacture products have surcharge rates that depend on the type of product being used.
You need to set up the costing sheet to include surcharges for specific items.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-335 Exam Question 75
You are developing a new car audio system kit. The kit configuration has restrictions based on car model, speaker size, and other expression constraints.
You need to set up a new item for the car audio system.
How should you create the new product? To answer, select the appropriate option in the answer area.
NOTE:Each correct selection is worth one point.

You need to set up a new item for the car audio system.
How should you create the new product? To answer, select the appropriate option in the answer area.
NOTE:Each correct selection is worth one point.