MB-335 Exam Question 101
You need to address the ignition switch issue.
Which three actions should you perform? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Which three actions should you perform? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point.
MB-335 Exam Question 102
You need to configure the solution for the two issues the production manager reported.
How should you complete the configurations? To answer, move the appropriate configurations to the correct issues. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

How should you complete the configurations? To answer, move the appropriate configurations to the correct issues. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

MB-335 Exam Question 103
A manufacturer is implementing Dynamics 365 Supply Chain Management to create blends of oil and industrial lubricant.
The manufacturer requires detailed documentation for the production order process before manufacturing begins for the products. The shop floor must review, approve, and anticipate all production runs. Before production starts, the manufacturer wants to ensure that the order can be completed by a certain timeframe based on capacity.
You need to define the production life cycle stages.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

The manufacturer requires detailed documentation for the production order process before manufacturing begins for the products. The shop floor must review, approve, and anticipate all production runs. Before production starts, the manufacturer wants to ensure that the order can be completed by a certain timeframe based on capacity.
You need to define the production life cycle stages.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-335 Exam Question 104
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.