MB-335 Exam Question 6

A company overstates on-hand raw materials due to the time it takes to post raw materials as consumed when production orders are processed.
All items used to manufacture finished goods must be consumed when a finished good is reported as finished.
You must not change all bill of materials lines to use the option of flushing principal.
You need to ensure that all production orders consume raw materials at Report as finished.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-335 Exam Question 7

You need to meet the needs for the large teakwood furniture order.
What must you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

MB-335 Exam Question 8

You need to meet the substitution requirements for User4 and User5.
What must you configure? To answer, drag the appropriate configurations to the correct substitution requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

MB-335 Exam Question 9

A company uses engineering change management in Dynamics 365 Supply Chain Management. The Product readiness checks feature is turned off.
An existing engineering product must be reconfigured for a new product readiness policy.
You need to change the product readiness policy.
Where should you make this change?
  • MB-335 Exam Question 10

    A company uses Dynamics 365 Supply Chain Management. Equipment installations in multiple regional locations require monthly maintenance.
    Two maintenance technicians have holiday time off scheduled this month.
    You need to ensure that all scheduled work orders are completed within the month around the holiday schedules.
    Which feature should you use?