    You are a project manager managing a large construction project. One of the pieces of heavy equipment required to dig the Foundation will most likely not be available until a specific date, because that equipment has been allocated to another, higher priority project. In that related project schedule you clearly see that in all likelihood, the activity in that plan that uses that equipment will also slip. You want to reflect this in your project schedule using a constraint. What would be the most appropriate constraint to use?