1Z0-129 Exam Question 66
A field has been configured on a contract to show the total amount of approved change orders for a contract. In order for this value to display, what must be set up in the Unifier once the configurations have been deployed?
1Z0-129 Exam Question 67
You are a Program Manager reviewing Portfolio Performance dat
a. You see a number of Issues that are assigned to a Responsible Manager. What does Responsible Manager mean within Primavera P6 EPPM?
a. You see a number of Issues that are assigned to a Responsible Manager. What does Responsible Manager mean within Primavera P6 EPPM?
1Z0-129 Exam Question 68
Identify one new feature in Release 8 related to Resource Management.
1Z0-129 Exam Question 69
You can create a Calculated User Defined Field for which Subject Area?
1Z0-129 Exam Question 70
What does Schedule Preview do?