1Z0-129 Exam Question 66

A field has been configured on a contract to show the total amount of approved change orders for a contract. In order for this value to display, what must be set up in the Unifier once the configurations have been deployed?
  • 1Z0-129 Exam Question 67

    You are a Program Manager reviewing Portfolio Performance dat
    a. You see a number of Issues that are assigned to a Responsible Manager. What does Responsible Manager mean within Primavera P6 EPPM?
  • 1Z0-129 Exam Question 68

    Identify one new feature in Release 8 related to Resource Management.
  • 1Z0-129 Exam Question 69

    You can create a Calculated User Defined Field for which Subject Area?
  • 1Z0-129 Exam Question 70

    What does Schedule Preview do?