1z0-1075-22 Exam Question 1

You have been asked to set up cost estimates for 10 different purchased items. Which two steps could be used to accomplish this task?
  • 1z0-1075-22 Exam Question 2

    Identify three requirements fulfilled by nonstandard work orders.
  • 1z0-1075-22 Exam Question 3

    Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.
  • 1z0-1075-22 Exam Question 4

    Your customer hasthe following business requirement. There are two work definitions created in the application. One Work Definition for Engine Finished Good and other Work Definition for Pallet Finished Good. The Engine Finished Good item should have Pallet Finished Goodsas one of its component.
    Identify the way to establish the relationship between Pallet and Engine Work Definitions.
  • 1z0-1075-22 Exam Question 5

    A plantruns 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
    The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
    What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?