1z0-1075-22 Exam Question 6

Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
  • 1z0-1075-22 Exam Question 7

    You are in the process of defining a Standard Operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.
    Identify the setup that will fulfill this requirement.
  • 1z0-1075-22 Exam Question 8

    A Production Operator needs to load Work Order Transactions from an external system into Manufacturing Cloud.
    Identify the correct sequence of tasks to be performed.
  • 1z0-1075-22 Exam Question 9

    During a Manufacturing Cloud implementation, the customer request to develop Oracle Transactional Business Intelligence reports that are not available out-of- the box.
    Identify the tool that is available to the Report Developer in Manufacturing Cloud to develop the reports.
  • 1z0-1075-22 Exam Question 10

    Identify two conditions that should be met at the same time for a Standard Operation to be called an Optional Operation.