ISO-9001-Lead-Auditor Exam Question 111

Scenario 5: Mechanical-Electro (ME) Audit Stages
Mechanical-Electro, better known as ME, is an American company that provides mechanical and electrical services in China. Their services range from air-conditioning systems, ventilation systems, plumbing, to installation of electrical equipment in automobile plants, electronic manufacturing facilities, and food processing plants.
Due to the fierce competition from local Chinese companies and failing to meet customer requirements, ME ' s revenue dropped significantly. In addition, customers ' trust and confidence in the company decreased, and the reputation of the company was damaged.
In light of these developments, the top management of ME decided to implement a quality management system (QMS) based on ISO 9001. After having an effective QMS in place for over a year, they applied for a certification audit.
A team of four auditors was appointed for the audit, including Li Na as the audit team leader. Initially, the audit team conducted a general review of ME ' s documents, including the quality policy, operational procedures, inventory lists, QMS scope, process documentation, training records, and previous audit reports.
Li Na stated that this would allow the team to maintain a systematic and structured approach to gathering documents for all audit stages. While reviewing the documented information, the team observed some minor issues but did not identify any major nonconformities. Therefore, Li Na claimed that it was not necessary to prepare a report or conduct a meeting with ME ' s representatives at that stage of the audit. She stated that all areas of concern would be discussed in the next phase of the audit.
Following the on-site activities and the opening meeting with ME ' s top management, the audit team structured an audit test plan to verify whether ME's QMS conformed to Clause 8.2.1 (Customer Communication) of ISO 9001.
To do so, they gathered information through group interviews and sampling. Li Na conducted interviews with departmental managers in the first group and then with top management. In addition, she chose a sampling method that sufficiently represented customer complaints from both areas of ME ' s operations.
The team members were responsible for the sampling procedure. They selected a sample size of 4 out of 45 customer complaints received weekly for electrical services and 2 out of 10 complaints for mechanical services.
Afterward, the audit team evaluated the evidence against the audit criteria and generated the audit findings.
Li Na chose a sampling method that sufficiently represents customer complaints from both areas of ME's operations. Which sampling method fits that description?
  • ISO-9001-Lead-Auditor Exam Question 112

    You work for an organisation, ' ABC ' , which provides packaged food to the public. You are asked to lead a team (you as the leader and two other auditors) to audit an external provider, ' XYZ ' , which provides packaging materials to your organisation. It is
    4 pm, and the audit is dlose to an end;
    you are having an internal meeting with the team to decide what will be presented to the auditee during the Closing meeting. The Closing meeting was scheduled for 5 pm.
    ' XYZ ' has two manufacturing lines: M1 is a clean room for primary packaging materials (i.e. will be in direct contact with the food), and M2 is for secondary materials (i.e. will not be in direct contact with food).
    Auditor 1 audited the two manufacturing lines.
    You: " What findings would you report? "
    Auditor 1: " I have one issue. Earlier today in the morning I saw some secondary material stocked in the clean room. I would propose raising a nonconformity. " You: " How would you write the nonconformity? " Auditor 1: " In the clean room, there was a pallet with secondary materials. " What additional information would you add to this text to complete the nonconformity report? Select six.
  • ISO-9001-Lead-Auditor Exam Question 113

    Which two of the following roles do not contribute to the audit outcomes?
  • ISO-9001-Lead-Auditor Exam Question 114

    (Which of the following two activities can be carried out on-site by an auditor with no human interaction ?)
  • ISO-9001-Lead-Auditor Exam Question 115

    You are leading a Stage 2 certification audit of a multi-site organisation and have received the audit schedule below; Head Office and Site 1 - Day 1 Site 2 (150 Km from HQ) - Days 2 and 3 During Day 1 of the audit, the dient informs you that the laboratory at Site 2 has been dosed for decontamination due to a serious outbreak of an infectious disease among workers. In Site 2, all other functions could be audited as planned.
    As the audit team leader, what would you do?
    Choose the best acceptable action you could take:
    Ask the audit Programme Manager for direction.
    Complete the audit on day 3 and report back to the certification body for a certification decision.
    Continue the audit on days 2 and 3 and return later to audit the Site 2 laboratory.
    Immediately cancel the audit since the audit plan cannot be completed.
    Who has the responsibility for assigning work to the audit team?