When cost variance is negative and schedule variance is positive, the project is:
Correct Answer: D
CAPM Exam Question 212
The following is a network diagram for a project. What is the critical path for the project?
Correct Answer: C
Section: Volume B
CAPM Exam Question 213
Which of the following are processes associated with Project Cost Management?
Correct Answer: C
Section: Volume E Explanation/Reference: https://blog.masterofproject.com/cost-management/
CAPM Exam Question 214
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Correct Answer: D
Explanation/Reference: Explanation: 6.4.3.2 Resource Breakdown Structure The resource breakdown structure is a hierarchical representation of resources by category and type. Examples of resource categories include labor, material, equipment, and supplies. Resource types may include the skill level, grade level, or other information as appropriate to the project. The resource breakdown structure is useful for organizing and reporting project schedule data with resource utilization information. Process: 6.4 Estimate Activity Resources Definition: Activity Resources is the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity. Key Benefit: The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates. Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Resource calendars 5. Risk register 6. Activity cost estimates 7. Enterprise environmental factors 8. Organizational process assets Tools & Techniques 1. Expert judgment 2. Alternative analysis 3. Published estimating data 4. Bottom-up estimating 5. Project management software Outputs 1. Activity resource requirements 2. Resource breakdown structure 3. Project documents updates
CAPM Exam Question 215
Cost variance (CV) is equal to earned value:
Correct Answer: A
Explanation/Reference: Explanation: CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV