CAPM Exam Question 266
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is
$50, and the earned value (EV) is $25?
$50, and the earned value (EV) is $25?
CAPM Exam Question 267
A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge.
Which dimension of PMI's Talent Triangle best relates to this need to improve?
Which dimension of PMI's Talent Triangle best relates to this need to improve?
CAPM Exam Question 268
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
CAPM Exam Question 269
The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

The shortest non-critical path for the project is how many days in duration?
CAPM Exam Question 270
A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?