PMI-ACP Exam Question 131

The initial roadmap and release dates for an agile project were set based on data from similar projects and some expert opinions. Halfway through the project, however, the team's estimates are different. Based on the team's velocity, two more iterations were necessary to accomplish the initial scope.
How should the agile lead explain the difference to the project sponsor?
  • PMI-ACP Exam Question 132

    A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.
    What should the agile practitioner do?
  • PMI-ACP Exam Question 133

    Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item.
    What should the agile project manager do?
  • PMI-ACP Exam Question 134

    A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets.
    To address this issue and bring the project back on track, what action should the team take?
  • PMI-ACP Exam Question 135

    A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?