PMI-PBA Exam Question 121
After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?
PMI-PBA Exam Question 122
A company has completed a major project within time. cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment From the business analysis perspective, the main reason for this business failure was a failure to: