PMI-PBA Exam Question 1

In the first few weeks after a large implementation of a new web-based application, a critical report failed.
Further Investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.
Which technique could have prevented this problem from occurring?
  • PMI-PBA Exam Question 2

    The document that defines the process for managing requirements revisions is the:
  • PMI-PBA Exam Question 3

    When modeling processes or analyzing tasks, business rules can be uncovered by asking about:
  • PMI-PBA Exam Question 4

    A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?
  • PMI-PBA Exam Question 5

    The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release.
    Which is a possible reason why the requirement was not implemented?