PMI-PBA Exam Question 21

Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?
  • PMI-PBA Exam Question 22

    During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?
  • PMI-PBA Exam Question 23

    A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume reporting required by the company's financial department. The business analyst for the project determines that the selection criteria needed was not specified in the system requirements or design specifications.
    Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement was missed?
  • PMI-PBA Exam Question 24

    A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper,"
    "Customer," and "Agent." These user groups
    categorize stakeholders with similar needs and create a detailed narrative.
    Which technique did the business analyst use for evaluating the solution's acceptance criteria?
  • PMI-PBA Exam Question 25

    A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.
    The business analyst tells the stakeholder that the requirement status was changed to "deferred " What could have prevented the stakeholder from being surprised about the status change?