PMP Exam Question 661
You are the project manager for a construction company. Your firm has been contracted to complete the construction of a 10-story office building. This project will use three point estimates to calculate the estimates for activity duration. You have the following estimates for task A (creating the foundation). Assuming the triangular distribution what is the average duration estimate based on the following three point estimates?
Pessimistic= 100 days
Optimistic= 40 days
Most likely=65 days
Pessimistic= 100 days
Optimistic= 40 days
Most likely=65 days
PMP Exam Question 662
Planning components are tools/ techniques of the Activity Definition Process. Which of the following are planning components?
PMP Exam Question 663
Change requests include a group of potential changes to a project. Types of change requests include all the following EXCEPT______________
PMP Exam Question 664
The project team directory is an output from which of the following processes?
PMP Exam Question 665
Project managers need exceptionally good communication and negotiation skills primarily because: