PMP Exam Question 861

Assume that your actual costs are $800; your planned value is $1,200; and your earned value is $1,000.
Based on these data, what can be determined regarding your schedule variance?
  • PMP Exam Question 862

    What component of the project scope definition defines project exclusions?
  • PMP Exam Question 863

    All of the following statements are true regarding the cost control process EXCEPT:
  • PMP Exam Question 864

    You are managing a social health insurance project. You are in the testing phase of the project, and the customer has requested additional requirements. A change request has been initiated. What should you do first regarding this request?
  • PMP Exam Question 865

    A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?