PMP Exam Question 906

Standard of purchased material:
  • PMP Exam Question 907

    Activity A is worth $200, is 100% complete, and actually cost $200. Activity B is worth $75, is 90% complete, and actually cost $120 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1000. What is the estimate at completion for the activities listed?
  • PMP Exam Question 908

    The following table shows the business value created and the development effort required to implement various features in a product

    Which feature should the team prioritize first? Enter the feature name in the box below

    PMP Exam Question 909

    A project manager is working on a project will components supported by two teams in two different regions. The project manager schedules a call with both teams to solicit estimates for a new requirement. Upon receipt of the two estimates, the project manager is surprised to see that they deviate from what was expected.
    What should project manager have done to avoid this?
  • PMP Exam Question 910

    What is the primary purpose of a milestone chart?