PMP Exam Question 16

CIP is:
  • PMP Exam Question 17

    Contract negotiations are NOT required when______________
  • PMP Exam Question 18

    What is the main purpose of project initiation?
  • PMP Exam Question 19

    In a project, a Cost incentive contract has been awarded to a contractor with the following parameters:
    Target cost: $1,000,000 Target contractor fee: $100,000 Cost benefit sharing ratio: 80%/20% Price ceiling: $1,200,000
    What is the Point of total assumption (PTA, Breakpoint) of the project?
  • PMP Exam Question 20

    A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).