PMP Exam Question 81

A complex, high-value agile project includes sprint demonstrations with the customer every four weeks. Executive management is concerned about the project's progress and wants more frequent updates on the project status.
What should the project manager do?
  • PMP Exam Question 82

    A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract What should the project manager do?
  • PMP Exam Question 83

    An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.
    What should the project manager recommend?
  • PMP Exam Question 84

    The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
  • PMP Exam Question 85

    A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?