PMP Exam Question 351

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.
What should the project manager do to help move the project forward?
  • PMP Exam Question 352

    A project manager is working on a project with multiple workstreams. One of the workstreams missed its deadline multiple times.
    Who should the project manager speak to about this situation to ensure it does not happen again?
  • PMP Exam Question 353

    A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.
    What should the project manager do?
  • PMP Exam Question 354

    A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.
    How can the project manager convey these benefits to the stakeholders?
  • PMP Exam Question 355

    A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.
    What else does the project manager need to do before determining the budget baseline?