PMP Exam Question 51

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.
What should the project manager have done to prevent this?
  • PMP Exam Question 52

    A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.
    What is the project manager doing?
  • PMP Exam Question 53

    A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
    What should the project manager do?
  • PMP Exam Question 54

    A company has started developing a new product. During execution the project team notices that another competitor has launched a product with very similar functionalities and a cheaper market price.
    What should have been done differently to avoid this scenario?
  • PMP Exam Question 55

    A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
    Which two actions should the project manager leverage to ensure the team is meeting performance expectations?
    (Choose two)