PMP Exam Question 691

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing.
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
What is the EAC for this project, and what does it represent?
  • PMP Exam Question 692

    Consider the project integration management knowledge area. Which of the following process are NOT included?
  • PMP Exam Question 693

    A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

    PMP Exam Question 694

    Which of the following tools and techniques is used to estimate cost?
  • PMP Exam Question 695

    An approach to provide insight into the health of the project and to identify any areas that require special attention is to______________