PMP Exam Question 1

At the beginning of a project, a project manager is asked to provide human resources (HR) with an evaluation of every team member's performance. This evaluation will be delivered at the end of the project.
How should the project manager approach this request?
  • PMP Exam Question 2

    Hotspot Question
    A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late.
    Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
    Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck.

    PMP Exam Question 3

    A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
    What should the project manager do?
  • PMP Exam Question 4

    A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.
    What should the project manager do first?
  • PMP Exam Question 5

    A project manager is leading a project team composed of members with varying levels of knowledge and experience. Some are experts and some have less than 1 year of experience.
    The project schedule was approved by the steering committee.
    What should the project manager do?