PMP Exam Question 186
A vendor supplying a piece of specialized equipment for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier. To stay on schedule, the vendor proposed replacing the sub-supplier's component with a similar part that is different from the one that is stipulated in the project specifications.
What should the project manager do next?
What should the project manager do next?
PMP Exam Question 187
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages. The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope.
What should the project manager do?
What should the project manager do?
PMP Exam Question 188
As a member of an organizational change management team, a project manager must pass on any changes to the project team. The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change.
What should the project manager do?
What should the project manager do?
PMP Exam Question 189
A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?
PMP Exam Question 190
A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for the project. The customer has informed the project manager to disregard the group as they are not in support of the project.
What should the project manager do next?
What should the project manager do next?