PMP Exam Question 16
A project manager is creating the quality management plan for deliverables with very precise requirements.
The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.
Which two actions should the project manager take first? (Choose 2)
The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.
Which two actions should the project manager take first? (Choose 2)
PMP Exam Question 17
A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.
What should the project manager have done to prevent this?
What should the project manager have done to prevent this?
PMP Exam Question 18
The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).
What should the project manager do?
What should the project manager do?
PMP Exam Question 19
A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.
What should the project manager do?
What should the project manager do?
PMP Exam Question 20
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
What should the project manager do to support the backlog prioritization?