PMP Exam Question 41

A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
  • PMP Exam Question 42

    A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
    What should the project manager do to support the backlog prioritization?
  • PMP Exam Question 43

    A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs) reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.
    Which document should the project manager update first to document this change?
  • PMP Exam Question 44

    Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.
    What should the project manager do to obtain agreement from both companies and acceptance from marketing?
  • PMP Exam Question 45

    A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.
    What should the project manager do?