PMP Exam Question 81
A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.
What should the project manager do first?
What should the project manager do first?
PMP Exam Question 82
While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.
What should the scrum master do?
What should the scrum master do?
PMP Exam Question 83
A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?
What should the project manager do next?
PMP Exam Question 84
Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.
What should the project manager do next?
What should the project manager do next?
PMP Exam Question 85
A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this project?
What should the project manager do to ensure that key stakeholders are available for this project?