PMP Exam Question 696

A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.
What should the project manager do first?
  • PMP Exam Question 697

    The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action What two actions should the project manager take'? (Choose two)
  • PMP Exam Question 698

    In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4 months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the following resources:
    * Two engineers (monthly salary of US$700 each)
    * One project manager (monthly salary of US$1,600)
    * Additional estimated monthly expenses of US$2,000
    The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house resources.
    How much money will the project manager estimate the company can save?
  • PMP Exam Question 699

    A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.
    What should the project manager do to have a high-performing team?
  • PMP Exam Question 700

    During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.
    What should the project manager do first?