PMP Exam Question 26
A project manager has just been assigned a major, ongoing project. The project team is not working in harmony and their performance is decreasing. Some team members are autocratic in their approach whereas others are in avoidance mode.
How should the project manager proceed?
How should the project manager proceed?
PMP Exam Question 27
A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the deployment.
What should the project manager have done to prevent the delay?
What should the project manager have done to prevent the delay?
PMP Exam Question 28
During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?
What should the project manager do to prioritize this critical impediment?
PMP Exam Question 29
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project.
The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
PMP Exam Question 30
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
What should the project manager do to manage business concerns and expectations before starting the project?