PMP Exam Question 466

A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.
How should the project lead respond?
  • PMP Exam Question 467

    A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.
    What should the project manager do to ensure the velocity is under control?
  • PMP Exam Question 468

    The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
    What should the project manager do?
  • PMP Exam Question 469

    A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.
    What should the project manager do?
  • PMP Exam Question 470

    Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?