PMP Exam Question 191

A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.
What should the project manager do first?
  • PMP Exam Question 192

    A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.
    Which two documents should the project manager update as soon as possible? (Choose two)
  • PMP Exam Question 193

    A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment What should the project manager do?
  • PMP Exam Question 194

    A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.
    What should the project manager do?
  • PMP Exam Question 195

    A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
    Which two actions should the project manager leverage to ensure the team is meeting performance expectations?
    (Choose two)