PfMP Exam Question 56

The Portfolio Management Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Management Plan purpose and focus?
  • PfMP Exam Question 57

    Managing Strategic Change is an integral part of any portfolio in order to remain aligned with the strategic objectives. Your portfolio has undergone a major strategic change and you are currently determining if, when, what, and how of implementing the change in order to re-align the portfolio. What are you currently doing?
  • PfMP Exam Question 58

    Along your portfolio lifecycle, you have been conducting multiple review meetings to ensure continuation from one phase to another and to ensure the alignment and value delivery, in addition to communicating decisions and valuable information to the related stakeholders. Changes to the approach of portfolio governance may be a result of review meetings. Which of the following options include updates to the governance model?
  • PfMP Exam Question 59

    You have been recently assigned to manage a new portfolio that is supposed to shift the company from silo-based to a projectized one. You are in the process of initiating the portfolio. You are currently developing the strategic plan. Upon finishing it, you are expected to present
  • PfMP Exam Question 60

    One of your components' managers came to you stating that she cannot find a key stakeholder by email and if she cannot find him, a major decision will be delayed, thus affecting the entire portfolio. What should you, as a portfolio manager do?