PfMP Exam Question 76

Multiple changes have been recommended and approved in your portfolio and the need for continuous optimization seems to never end. This is normal in a portfolio and optimizing the components mix and the use of resources is key to success. As a portfolio manager you will be re-visiting the Optimize Portfolio process countless times. Which of the following are considered outputs to this process?
  • PfMP Exam Question 77

    You have scored the portfolio components and are analyzing the data in order to prioritize the components.
    Using the following scoring table, which of the options represents the correct Components Priority? Taking into consideration that the costs for each component is Component A: 10 K USD, Component B: 15 K USD, Component C: 16 K USD, Component D: 13 K USD and Component E: 11 K USD; The budget for this portfolio is a fixed one of 40 k USD Larger image
  • PfMP Exam Question 78

    You are mid-way through your portfolio and you are approaching a major milestone where multiple components will be authorized for execution and implementation. For informed decision making, as a portfolio manager, you will be communicating reports that will be viewed and analyzed, and used as critical information for taking a decision for the authorization of components. After passing through the authorization process, multiple reports are generated and others are updated. What type of reports is generated from this process?
  • PfMP Exam Question 79

    You are the manager of a major portfolio with a critical strategic objective. You have just finalized the roadmap development and wanted to have a quick discussion on it with the team. One of your team members asks you your opinion on the relation between Portfolio roadmap and Strategic Objectives. What would your answer be?
  • PfMP Exam Question 80

    One of the stakeholders of one of your components came to you complaining that his manager is not receiving specific information on multiple components progress. What is your best course of action?