PfMP Exam Question 206

You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. When it comes to Portfolio dependencies, which of the following is true regarding the roadmap?
  • PfMP Exam Question 207

    You are currently defining a hierarchical representation of your portfolio and its components and listing the major and milestone components, including dependencies internal and external to the portfolio with business units. For this you know that you will need multiple inputs. Which of the following are considered inputs in your case?
  • PfMP Exam Question 208

    You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust performance management plan. What is expected to be found in this plan?
  • PfMP Exam Question 209

    The portfolio undergoes a lot of changes through the portfolio life cycle, and the state of the portfolio changes on the go. Some components are terminated, other are added and initiated. When it comes to the authorize portfolio process, which of the following represents the state of the portfolio
  • PfMP Exam Question 210

    When it comes to managing a portfolio, you have a variety of assets, plans and tools and techniques used. It requires a good experience to handle all of these artifacts. One of your portfolio team members came to you asking about the relation between the portfolio performance management plan, the portfolio management plan and portfolio strategic plan. What should your answer be?