PfMP Exam Question 226

Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. Risk is part of project, program and portfolio management and has a different exposure in each and every one. When it comes to Managing portfolio risks, a risk owner, along with the portfolio manager, should select the strategy or mix of strategies most likely to be effective. Which of the following may be the responsibility of a risk owner when it comes to managing risks?
  • PfMP Exam Question 227

    Your company works closely with the government on the implementation of water pumps for rural areas. You are constantly dealing with new and updated regulations, and periodically adapting the portfolio to the changes. When it comes to regulatory components, how do you include the components in the portfolio?
  • PfMP Exam Question 228

    A new portfolio is initiated with you as the portfolio manager, you started by developing the portfolio strategic plan and are currently reviewing the Organizational Process Assets; which of the options can be a part of this input?
  • PfMP Exam Question 229

    Assume at this point as the portfolio manager in your mattress company, you are activating portfolio components, updating portfolio reports, and documenting the decisions made at the recent Portfolio Governance Committee meeting as the company moves into new markets. You are therefore:
  • PfMP Exam Question 230

    You have just finished the development of the Portfolio Communication Management Plan. The portfolio team is looking for portfolio value assessment, status reports, and portfolio forecast with variance to plan. Where should they find this information?