PgMP Exam Question 56

As a Program Manager, you decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?
  • PgMP Exam Question 57

    You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are telling Beth about the five process groups of project management and how they map to the progression of the project. Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?
  • PgMP Exam Question 58

    Your program has a budget at completion of $1,550,000 and is expected to last one year.
    Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?
  • PgMP Exam Question 59

    A program manager for the construction of an international event venue that will impact the local community needs to determine the best approach for communications. One of the conditions of the program is that after the event takes place, a park will be built for the community's use.
    What should the program manager do to ensure community support?
  • PgMP Exam Question 60

    A large international manufacturing company is centralizing its IT which is currently spread over 16 countries.
    The transition means physically regrouping the infrastructure and aligning processes and organizations. The high-level scope of this transformation encompasses three main areas:
    1.The technology area--assessing which technology/tooling should be retained for the target data center.
    2.The policies and procedure area--aimed at establishing a common set of processes supporting the new way of delivering services.
    3.The HR area--assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions.
    You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase.
    Which document should be present in your business case?