PgMP Exam Question 321

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
  • PgMP Exam Question 322

    A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization.
    At the next stakeholder meeting, what should the program manager present to address their concerns?
  • PgMP Exam Question 323

    A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
    What should the program manager do next?