PgMP Exam Question 316
You are the program manage of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects.
What document names the project manager for the project?
What document names the project manager for the project?
PgMP Exam Question 317
In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?
PgMP Exam Question 318
Program manager B leaves the program and program manager A takes over the program responsibilities.
Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?
Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?
PgMP Exam Question 319
You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?
PgMP Exam Question 320
Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?