Question 1

If, at the end of each stage, circumstances external to the project had changed which affect the project's costs, risks and benefits, which product should be updated to reflect this?

Question 2

There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?

Question 3

Which process would check and accept Work Packages?

Question 4

If, for whatever reason, the business justification disappears once the project is underway, what does PRINCE2 suggest should happen?

Question 5

Which is an objective of the Managing a Stage Boundary process?