PRINCE2-Practitioner Exam Question 46

Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the service level agreement (SLA) with the selected service provider?
  • PRINCE2-Practitioner Exam Question 47

    Scenario
    Additional Information
    Product Description

    Quality notes from the Daily Log
    The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
    The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
    MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
    All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
    Extract from the draft Quality Management Strategy (may contain errors) Introduction
    1. This document defines the approach to be taken to achieve the required quality levels during the project.
    2. The Project Board will have overall responsibility for the Quality Management Strategy.
    3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
    Quality management procedure - Quality standards
    4. The selected service provider will operate to industry standards for providing outsourced services.
    5. MFH document standards will be used.
    Records
    6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
    7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
    8. Approval records for products that require them will be stored in the quality database.
    Roles and responsibilities
    9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
    10. Team Managers will provide details of quality checks that have been carried out.
    11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
    12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
    Which is a correctly defined acceptance criterion for the running cost of the outsourced service?
  • PRINCE2-Practitioner Exam Question 48

    Scenario
    Additional Information
    Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
    Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
    Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
    Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
    Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
    Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet been decided which of the photographers to use.
    Which 2 statements explain why the CEO should be appointed as the Executive for this project?
  • PRINCE2-Practitioner Exam Question 49

    Project Scenario
    Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
    * Design for each month - correctly showing at public holidays and new company logo
    * Selected photographs- 12 professionally-produced photographs, showing different members of staff
    * Selected paper and selected envelope - for printing and mailing the calendar
    * Chosen label design - a competition to design a label will be held as part of this project
    * List of customers - names and addresses of customers to whom the calendar will be sent.
    The project is currently in initiation and will have two further stages:
    Stage 2 will include tie activities to:
    * Create the customer fast using information from the Accounts and Marketing departments
    * Confirm compliance with the Data Protection Legislation
    * Create a design for each month - this will be done by the internal creative team
    * Select and appoint a professional photographer
    * Gather photograph design ideas from previous project and agree photographic session schedule
    * Prepare a production cost forecast
    * Select paper and envelope.
    Stage 3 will include the activities to:
    * Produce and select tie professionally-taken photographs
    * Hold the label design competition and choose the label design
    * Assemble the prepared calendar pack.
    A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
    It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
    As the project approaches the end of stage 2, the Project Manager has requested a Product Status Account to ensure that all products are at their expected point of development. Although the list of customers has been quality reviewed, it has not been baselined because the Marketing department have not provided all of the prospective customers' details. What initial action should the Project Manager take?
  • PRINCE2-Practitioner Exam Question 50

    Additional Information
    Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
    Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
    Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
    Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
    Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
    Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet to be decided which of the photographers to use.
    Using the additional Information provided for this question In the Scenario Booklet, answer the following question.
    Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.