Question 1

While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled?
Please choose the correct answer.
Response:

Question 2

Which type of confirmation allows you to confirm various networks, activities, activity elements, and individual capacities at the same time?
Please choose the correct answer.
Response:

Question 3

A costumer uses cross-company-code projects with a top billing element and an additional billing element underneath for each company code. Although the internal billing between the lower-level WBS elements has been performed correctly, the results analysis summarizes all values to the highest billing elements.
How can we split the results to the different company codes? *

Question 4

When you assign material components using the BOM transfer function, the system uses the Reference Point field in the BOM items and activities to establish a logical connection between which items?
There are 2 correct answers to this question.
Response:

Question 5

How do you evaluate and display details of orders and networks that create capacityrequirements at the work centers?
Please choose the correct answer.
Response: