You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.
What controls whether the delivery date is defined by the earliest or latest scheduled dates?
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?